Thompson Peak Parkway carries four lanes of traffic and two bike lanes until it reaches Reata Wash. On the bridge over the wash, the four lanes merge into two, and the bike lanes cross alongside them. On the far side the road widens back out. For anyone driving between Silverleaf and the rest of DC Ranch, that merge is a normal part of the trip.
The road was planned with a second bridge from the beginning. Work on it was scheduled to start Monday, Nov. 2.
A Bridge Designed Twice and Built Once
The City of Scottsdale's project page explains the history. When DC Ranch was built, the city and the developer signed an agreement that required the developer to design both Thompson Peak Parkway bridges over Reata Wash. It only had to build one, because the new community didn't yet have enough traffic to need two. The deal also left the city responsible for building the second bridge once traffic grew enough to justify it.
Car traffic turned out not to be the problem. The city says the existing bridge has handled vehicle volume as the area developed. The safety concern for drivers and cyclists comes from the rise in bicycle traffic on this part of the road. Two lanes of cars and two bike lanes now cross a bridge that sits between four-lane sections in both directions, and the merge happens right where the riders are.
The new bridge will be a two-lane span that mirrors the existing one, with bike lanes and a sidewalk. Once it's done, Thompson Peak Parkway will run as a continuous four-lane road with bike lanes from Scottsdale Road to 100th Street. The city calls this the road's "ultimate cross-section."
How a Bond Line Item Became a $14.2 Million Project
Voters approved the money in the 2019 Bond Election, under Question 2, Community Spaces and Infrastructure. It was listed as Project 62: "Build a Bridge on Thompson Peak Parkway Bridge over Reata Pass Wash to Improve Safety." According to the DC Ranch Association's bridge updates page, the community pushed hard for the expansion, and it ended up as the only transportation project in that bond package.
The cost has grown since then. Scottsdale Progress reported that the voter-approved package included $6.3 million for the bridge. Ahead of the Sept. 22 council meeting, the low-bid construction contract alone came to about $8 million. The paper quoted the city staff report on the safety case:
"Currently, the four lanes of traffic that travel Thompson Peak Parkway merge into two travel lanes over the existing bridge."
The same report said the contract also covers a public art component and minor improvements to the existing bridge.
On Tuesday, Sept. 22, 2026, the Scottsdale City Council approved Resolution 13778 on its consent agenda. The resolution authorizes Contract 27IBF097 with Ames Construction, Inc. for up to $8,085,461.26. The contract is only part of the total. The city lists an overall project budget of $14.2 million. The project page names two funding sources, the 2019 bond and the 0.2% Transportation Sales Tax.
What the DC Ranch Community Council Asked For
This bridge sits in a community with a well-defined look, so the city brought its early drawings to the DC Ranch Community Council in July 2026. After reviewing them with city staff, the board sent back the following feedback, according to the association's updates page:
- Fake stone is not acceptable. The stone should be DC Cobble, matching the original bridge.
- Jersey barriers along the full length of the bridge are also unacceptable. The board suggested dropping the sidewalk and continuing the natural path through the wash.
- Cutting the arched supports under the bridge isn't preferred, but the board understood the cost savings.
- Metal railings can replace wood if they match the original design. The board also asked that the original bridge's railings, which it described as in poor condition, be replaced with metal.
These are requests, and the city's current project page doesn't say which ones made it into the final plans. It still describes the new bridge as including a sidewalk. DC Ranch announced that the city would hold a public open house on the design and construction timeline on Sept. 9, from 5:30 to 7 p.m. at The Homestead.
The art comes through Scottsdale's Art in Public Places program, and the city's FY 2026/27 capital improvement plan lists publicly visible capital projects, bridges included, as part of that program. The same plan sets aside $111,200 for art on the Thompson Peak bridge. In other words, the Thompson Peak crossing will get a public art piece along with its second span.
The design work started well before this fall. In 2025, DC Ranch reported that the city had hired Kimley-Horn as the design consultant and that its team was doing the required environmental and cultural resource surveys on site so the project could go out to bid.
The First Phase Happens Down in the Wash
The early work stays out of the travel lanes, so drivers on Thompson Peak Parkway won't see much of it at first. According to the city's Oct. 16 notice, crews work Monday through Friday, 7 a.m. to 5 p.m., and the first phase covers:
- Salvaging and relocating native plants.
- Finding underground utilities and possibly relocating them.
- Drilling shafts for the bridge supports.
Much of this work happens below grade in Reata Wash, and the city says travel lanes won't be affected during this phase. The contractor's staging area and a temporary plant nursery will be on site. The nursery explains a lot about the first stretch of work. Desert plants dug out of the wash will be kept nearby during construction.
DC Ranch's own trail maps include a route named Reata Wash/Thompson Peak Pkwy., one of several marked community routes alongside the Silverleaf Village Route and the Country Club Village Route. The city hasn't yet posted a schedule for later phases, including any lane shifts on the parkway or changes to paths near the bridge. Updates will appear on the city project page, which was last updated Oct. 16, 2026.
How Long the Squeeze Will Last
The city expects construction to take about 12 months. The timeline has moved before. In 2024, DC Ranch reported that the city's FY24/25 budget included design funding, with construction expected the following year. In 2025, the association said it had worked with the city to move the completion date up from 2028. For now, the city's current estimate is about 12 months of construction, counted from the scheduled Nov. 2 start.
When the work is finished, the two-lane merge over Reata Wash will be gone, and drivers and cyclists will have a continuous four-lane road with bike lanes from Scottsdale Road to 100th Street. That was the plan when DC Ranch was first designed.
Projects like this are part of what I track for clients around Silverleaf and DC Ranch, because a road's timeline can matter as much as the home itself when you're planning a move or a listing date. If you'd like to talk through what the Thompson Peak work means for your own plans this year, Lauren Ellington is glad to set up a confidential consultation.